Down, Down, Demolished!

 

As you will all have seen Units 1, 4 & 5 have now been demolished and we are currently breaking part of the old yard up and crushing materials on site.


We anticipate this being an ongoing process for another week or so and then we intend to commence works on units 17-20 and 9-12 ground preparation and foundations.

All being well we hope to begin diverting services such as water, drainage and gas in the coming weeks leading up to Christmas.


We are hoping that the steel frames for these two buildings will have begun prior to the Christmas break.